Vales Point Power Station

Client: Transgrid / Gongues Construction Pty Ltd
Location: Mannering Park, NSW
Sector: Power / Utilities

Scope of Works

  • Transformer (TX) footings.
  • Cable trench slabs and walls.
  • Slabs on ground.

 

Key Challenges

  • Stringent tolerances for equipment alignment and embedded conduits.
  • Working around existing live services and earthing grids.

 

Outcomes

  • Survey-controlled set-out with pre-pour hold points for embeds/bolts.
  • Plinths & Hold Down Bolts installed to millimetre tolerances; no rework for equipment install.
  • Full compliance with utility standards and inspection regimes.