Wahroonga Bridge

Location: Illoura Ave, Wahroonga
Sector: Bridges / Major Roads Infrastructure
Client: Haslin Constructions

Scope of Works:

Rodri Civil Constructions delivered the FRP concrete package across two stages, including:

  • Cast in-situ deck works, edge beams and diaphragms
  • Stitch pours to parapets
  • Approach slabs and transition slabs
  • Installation of cast-in items and bearing set-outs
  • Possession works to facilitate critical structural pours

All works were undertaken in accordance with TfNSW specifications and QA requirements.

 

Key Challenges:

  • Staged construction methodology requiring strict sequencing
  • Possession-based works with limited timeframes
  • Constrained residential access and traffic interface Outcomes:
  • Delivered structural elements on programme across both stages
  • Achieved high-quality finishes meeting TfNSW bridge standards